Clay Basin Storage
| Category | Preliminary Dates | Duration | Location | Project | Anticipated Firm Cut Quantity |
|---|---|---|---|---|---|
| Reservoir Testing | March 27 - April 7 | 13 Days | Clay Basin | Annual Withdawal Test | ALL |
| Pig |
April 1 |
1 Day |
JL46 |
Smart Tool | 0 Dth/d |
|
Pig |
April 2 |
1 Day |
ML 40 Pete's Wash to Fidlar |
Smart Tool |
0 Dth/d |
| Anomaly Digs | April 6 - May 9 | 7 Days | JL46/JL47 | Anomaly digs | TBD |
|
Pig |
April 7 - 9 |
3 Days |
ML 13 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
|
Pig |
April 9 |
1 Day |
ML 1 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
| Compressor Maintenance | April 20 - 24 | 5 days | Oak Springs Compressor Station | Station ESD Testing | TBD |
| Compressor Maintenance | April 27- May 1 | 5 Days | Simon Compressor Station | Station ESD Testing | 0 Dth/d |
|
Pig |
May 5 - 6 |
2 Days |
ML 2 Coalville to Little Mountain |
Smart Tool |
0 Dth/d |
|
Pig |
May 7 |
1 Day |
ML 14 Coalville to Little Mountain |
Smart Tool |
0 Dth/d |
| Compressor Maintenance | May 12 - 13 | 2 Days | Kanda Compressor Station | Station ESD Testing | ALL |
|
Pig |
May 13 - 14 |
2 Days |
ML 13 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
|
Pig |
May 18 - 19 |
2 Days |
ML 13 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
| Compressor Maintenance | May 18 - 22 | 5 Days | Leroy Compressor Station | Station ESD Testing | 0 Dth/d |
| Anomaly Digs | June 1- 10 | 10 Days | ML48/ML60 Junction | Anomaly Digs | 0 Dth/d |
|
Pig |
June 2 |
1 Day |
ML 104 Thistle to Goshen |
Smart Tool |
0 Dth/d |
| Compressor Maintenance | June 15 - 19 | 5 Days | Thistle Creek Compressor Station | Station ESD Testing | TBD |
|
Pig |
June 16 - 18 |
3 Days |
ML 2 Coalville to Little Mountain |
Smart Tool |
0 Dth/d |
|
Pig |
June 24 |
1 Day |
ML 14 Coalville to Little Mountain |
Smart Tool |
0 Dth/d |
| Anomaly Digs | July 6- 31 | 28 | ML 1, ML13, and ML15 from Nightingale to Eakin | Anomaly Digs | 0 Dth/d |
| Compressor Maintenance | July 7 - 8 | 2 Days | Coleman Compressor Station | Station ESD Testing | TBD |
|
Pig |
July 15 |
1 Day |
ML 104 Thistle to Goshen |
Smart Tool |
0 Dth/d |
|
Pig |
August 4 |
1 Day |
ML 1 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
| Anomaly Digs | Aug 3- 15 | 13 | ML22 and ML23 Skull Creek Compressor | Anomaly Digs | TBD |
|
Pig |
August 6 |
1 Day |
ML 1 Nightingale to Eakin |
Smart Tool |
0 Dth/d |
| Reservoir Testing | October 4 - 17 | 13 Days | Clay Basin | Annual Injection Test | ALL |
Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.
| Notice Type Desc | Subject | Post Date/Time |
|---|---|---|
| STORAGE/OFO/PLND OUTAGE | 2026 ANNUAL CLAY BASIN WITHDRAWAL TEST UPDATE | 03/04/2026 12:45 PM |
| PLND OUTAGE/MAINT/CONSTRAINT | REVISED SKULL CREEK COMPRESSOR ANNUAL ESD AND UNIT MAINTENANCE | 02/27/2026 12:45 PM |
| STORAGE/OFO/PLND OUTAGE | 2026 ANNUAL CLAY BASIN WITHDRAWAL TEST | 02/24/2026 02:30 PM |
| PLND OUTAGE/MAINT/CONSTRAINT | SKULL CREEK COMPRESSOR ANNUAL ESD AND UNIT MAINTENANCE | 02/24/2026 02:21 PM |
| OFO | MOUNTAINWEST PIPELINE OFO | 01/21/2026 02:51 PM |
| OTHER | NOTICE OF PERIODIC PURCHASES AND SALES OF NATURAL GAS | 05/01/2014 12:18 PM |
All listed times are CCT
MountainWest Fidlar Expansion Non-binding Open Season November 2024: Project Overview and Bid Sheet
MountainWest Uinta Basin Expansion II (UBE II) – September 2024: Project Overview & Bid Sheet
MountainWest Pipeline (MWP) held an open season from October 16, 2023 to November 16, 2023, to solicit bids for its proposed Uinta Basin Expansion (UBE) project. The UBE project would provide incremental firm transportation up to 113,300 Dth/d capacity from MWP’s Brundage Mountain meter station to the Chipeta Processing delivery point. MWP received anchor shipper bids from four shippers as part of the open season. As a result of the open season, and shipper elections in their open season bids, three of the four anchor shipper bidders were awarded a pro rata share of the entire amount of UBE project capacity. MWP has executed precedent agreements with the three winning bidders and filed a Prior Notice request with the FERC on January 16, 2024. MWP is targeting a July 1, 2024 in-service date for the UBE project facilities.
This Cost Estimate Request Form will be the basis for either NWP, MWP, MWOP or WRH Pipelines to determine the Customer's objectives for a new interconnect or modification of an existing interconnect with the Pipeline. Customer shall return this completed form to Pipeline for preliminary review by design engineering to define and verify the work scope and costs of the project.
When the Customer agrees to the scope of the work and estimated reimbursable cost of the Project, Pipeline will send Customer the Interconnect/Facility Agreement for review and execution. Payment of the estimated project cost will be made via the following:
1. An executed Transportation Service Agreement or a
2. Up-front payment including CIAC gross up or
3. Another option to be determined.
Upon receipt of the executed Interconnect/Facility Agreement and payment of project costs, Pipeline will proceed with engineering design, environmental clearance, material procurement and scheduling of construction of facilities. The entire process, from receipt of executed Agreement and payment can take approximately nine months to a year depending upon lead time for materials and scheduling of construction crews. Tap installations scheduled during winter months (December – February) may be subject to delays due to inclement weather or pipeline restrictions. Significant changes in the Customer's objectives after project authorization will affect the cost estimate and construction schedule.
Please click on this link: Cost Estimate Form and complete the online PDF form. Return this form and any additional attachments to a Williams Representative as listed on the Contacts page.
Please contact your Marketing Rep with any questions.
Please contact your Marketing Rep with any questions.
Please contact your Marketing Rep with any questions.
Pipeline Control Hotline:
713-215-2728
Emergency or Gas Leak:
713-215-2728
Scheduling Customer Hotline:
801-584-6034
Scheduling Group ICE Chat:
MWPScheduling