Maintenance Construction Schedule - MountainWest Overthrust Pipeline

2026 Schedule

Period Category Preliminary Dates Duration Location Project Possible Customer Impact Current Capacity (Dth/d) Restricted Capacity (Dth/d) Anticipated Firm Cut Quantity Anticipated Total Nomination Cut %
June Battery Charger Replacement June 23  1 Day Whitney Canyon Battery Charger Replacement MAP 10002 from 264,083 Dth/d to 0 Dth/d • MAP 10006 from 262,000 Dth/d to 0 Dth/d • MAP 10015 from 220,000 Dth/d to 0 Dth/d • MAP 10032 from 344,000 Dth/d to 0 Dth/d • MAP 10832 from 344,000 Dth/d to 0 Dth/d
 MAP 10002  264,083  Dth/d  • MAP 10006  262,000 Dth/d • MAP    10015 220,000 Dth/d     MAP 10032 344,000 Dth/d • MAP 10832 344,000 Dth/d  TBD ALL 100%
June

Pig
June 25 - 26

2 Days
ML 116 Labarge to Whitney Canyon

Smart Tool
Yes TBD TBD TBD TBD
July

Pig
July 22 - 24

3 Days
ML 116 Labarge to Whitney Canyon

Smart Tool
Yes TBD TBD TBD TBD
August Compressor Maintenance August 11 -14 4 Days Rock Springs Compressor Station Station ESD Testing All Compression Offline Capacity constraints at ML 122 Rendezvous, Whitney Canyon Constraint, MAP 10005 Kanda/Col, and MAP 10013 WIC RS Kanda/Coleman Segment: 410,000 Dth/d ML 122 Rendezvous: 1,151,000 Dth/d Whitney Canyon Constraint: 291,000 Dth/d MAP 10005 Kanda/Col: 173,667 Dth/d MAP 10013 WIC RS: 347,333 Dth/d TBD TBD
September Compressor Maintenance Sept 7 -11 5 Days Roberson Compressor Station Station ESD Testing YES TBD TBD TBD TBD

Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.