Maintenance Construction Schedule - MountainWest Overthrust Pipeline

2026 Schedule

Period Category Preliminary Dates Duration Location Project Possible Customer Impact Current Capacity (Dth/d) Restricted Capacity (Dth/d) Anticipated Firm Cut Quantity Anticipated Total Nomination Cut %
August

Pig
August 19

1 Day
ML 116 Labarge to Whitney Canyon

Smart Tool
None Whitney Canyon Segment: 345,000 Dth/d N/A 0 Dth/d 0%
September Compressor Maintenance September 29 and 30 2 Days Point of Rocks Compressor Station Station ESD Testing ML 122 Rendezvous: 1,683,000 Dth/d, Whitney Canyon: 200,000 Dth/d, Cabin 31: 1,861,000 Dth/d, Rock Springs East: 1,549,000 Dth/d, Wamsutter: 1,056,000 Dth/d.
ML 122 Rendezvous: 1,752,000 Dth/d,  Whitney Canyon: 345,000 Dth/d,  Cabin 31: 2,075,000 Dth/d,  Rock Springs East: 1,910,000 Dth/d,   Wamsutter: 1,265,000 Dth/d.
ML 122 Rendezvous: 1,683,000 Dth/d, Whitney Canyon: 200,000 Dth/d, Cabin 31: 1,861,000 Dth/d, Rock Springs East: 1,549,000 Dth/d, Wamsutter: 1,056,000 Dth/d.
Varies Not Available

Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.