| Period | Category | Preliminary Dates | Duration | Location | Project | Possible Customer Impact | Current Capacity (Dth/d) | Restricted Capacity (Dth/d) | Anticipated Firm Cut Quantity | Anticipated Total Nomination Cut % |
|---|---|---|---|---|---|---|---|---|---|---|
| March | Compressor Maintenance | March 3 - 5 | 3 Days | Fidlar Compressor Station | Station ESD Testing | All Compression Offline. Increased pressures at (MAP 370) Red Wash |
(MAP 370) Red Wash - Fidlar: 330,000 Dth/d | N/A | 0 Dth/d | 0% |
| March | Compressor Maintenance | March 4 | 1 Day | Skull Creek Compressor Station | Station ESD Testing | All Compression Offline |
(MAP 167) Skull Creek Delivery: 44,000 Dth/d (MAP 967) Skull Creek Reciept: 45,850 Dth/d |
(MAP 167) Skull Creek Delivery: 44,000 Dth/d (MAP 967) Skull Creek Receipt: 0 Dth/d |
ALL | 100% |
| March - April | Reservoir Testing | March 28 - April 9 | 13 Days | Clay Basin | Annual Withdawal Test | No physical injections allowed starting GD March 28 through GD March 30.
GD March 31, constant 250 MMcf/day WD rate. GD April 1, constant 275 MMcf/day WD rate. GD April 2 through GD April 8, reservoir shut-in Resume normal operations GD April 9. |
Varies, See latest EBB | Mar 31 Withdraw: 262,500 Dth/d Apr 1 Withdraw: 288,750 Dth/d Apr 2- Apr 8: 0 Dth/d |
ALL | 100% |
| April | Compressor Maintenance | April 20 - 24 | 5 days | Oak Springs Compressor Station | Station ESD Testing | Capacity reduction on ML 104 Goshen Segment of 120,000 Dth/d | ML 104 Goshen: 384,500 Dth/d | ML 104 Goshen: 264,500 Dth/d | TBD | TBD |
| April |
Compressor Maintenance | April 27- May 1 | 5 Days | Simon Compressor Station | Station ESD Testing | Capacity reduction on ML22 to Nightingale Segment of 27,650
Dth/d. Increased ML22 pressures for Vermillion Plant MAP 293,
Skull Creek Delivery MAP 167, Skull Creek Receipt MAP 967 |
Nightingale ML22 Segment: 206,650 Dth/d | Nightingale ML 22: 179,000 Dth/d | 0 Dth/d | 0% |
| May | Anomaly Digs | May 3 - 9 | 7 Days | JL46/JL47 | Anomaly digs | Reduced Flows on JL46 Myton and JL47 Myton Segments | JL 46 Myton: 66,200 Dth/d JL 47 Myton: 77,700 Dth/d |
TBD | TBD | TBD |
| May | Compressor Maintenance | May 12 - 13 | 2 Days | Kanda Compressor Station | Station ESD Testing | All Compression Offline Kanda/Col CIG DEL MAP 171 shut in Kanda/Col CIG REC MAP 871 shut in |
Kanda/Col CIG DEL MAP 171: 178,000 Dth/d Kanda/Col CIG REC MAP 871:138,000 Dth/d | Kanda/Col CIG DEL MAP 171: 0 Dth/d Kanda/Col CIG REC MAP 871:0 Dth/d |
ALL | 100% |
| May | Compressor Maintenance | May 18 - 22 | 5 Days | Leroy Compressor Station | Station ESD Testing | No Injection or Withdraw at Leroy |
Aquifer Storage Injection: 61,200 Dth/d Aquifer Storage Withdraw: 134,900 Dth/d |
Aquifer Storage Injection 31,200 Dth/d Aquifer Storage Withdraw: 74,900 Dth/d |
0 Dth/d | 0% |
| June | Compressor Maintenance | June 15 - 19 | 5 Days | Thistle Creek Compressor Station | Station ESD Testing | All Compression Offline Lowered capacity on ML 104 Goshen Segment |
ML 104 Goshen Segment: 384,500 Dth/d |
ML 104 Goshen: 302,000 Dth/d |
TBD | TBD |
| July | Compressor Maintenance | July 7 - 8 | 2 Days | Coleman Compressor Station | Station ESD Testing | All Compression Offline | Kanda/Coleman Segment: 410,000 Dth/d | TBD | TBD | TBD |
| October | Reservoir Testing | October 4 - 17 | 13 Days | Clay Basin | Annual Injection Test | No physical withdraw allowed starting GD Oct 4 through GD Oct 6. GD Oct 6, constant 250 MMcf/day INJ rate. GD oct 7, constant 275 MMcf/day INJ rate. GD October 8 through GD October 15, reservoir shut-in
Resume normal operations GD October 16. |
Varies, See latest EBB | TBD | ALL | 100% |
Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.