Maintenance Construction Schedule - MountainWest Pipeline

2026 Schedule

Period Category Preliminary Dates Duration Location Project Possible Customer Impact Current Capacity (Dth/d) Restricted Capacity (Dth/d) Anticipated Firm Cut Quantity Anticipated Total Nomination Cut %
March Compressor Maintenance March 3 - 5 3 Days Fidlar Compressor Station Station ESD Testing All Compression Offline. 
Increased pressures at (MAP 370) Red Wash
(MAP 370) Red Wash - Fidlar: 330,000 Dth/d N/A 0 Dth/d 0%
March Compressor Maintenance March 4 1 Day Skull Creek Compressor Station Station ESD Testing All Compression Offline
(MAP 167) Skull Creek Delivery: 44,000 Dth/d
(MAP 967) Skull Creek Reciept: 45,850 Dth/d
(MAP 167) Skull Creek Delivery: 44,000 Dth/d
(MAP 967) Skull Creek Receipt: 0 Dth/d
ALL 100%
March - April Reservoir Testing March 28 - April 9 13 Days Clay Basin  Annual Withdawal Test No physical injections allowed starting GD March 28 through GD March 30.
GD March 31, constant 250 MMcf/day WD rate. 
GD April 1, constant 275 MMcf/day WD rate.
GD April 2 through GD April 8, reservoir shut-in
Resume normal operations GD April 9.
Varies, See latest EBB Mar 31 Withdraw: 262,500 Dth/d 
Apr 1 Withdraw: 288,750 Dth/d 
 Apr 2- Apr 8: 0 Dth/d
ALL 100%
April Compressor Maintenance April 20 - 24 5 days Oak Springs Compressor Station Station ESD Testing Capacity reduction on ML 104 Goshen Segment of 120,000 Dth/d ML 104 Goshen: 384,500 Dth/d ML 104 Goshen: 264,500 Dth/d TBD TBD
April
Compressor Maintenance April 27- May 1 5 Days Simon Compressor Station Station ESD Testing Capacity reduction on ML22 to Nightingale Segment of 27,650 Dth/d. 
Increased ML22 pressures for Vermillion Plant MAP 293, Skull Creek Delivery MAP 167, Skull Creek Receipt MAP 967
Nightingale ML22 Segment: 206,650 Dth/d  Nightingale ML 22: 179,000 Dth/d 0 Dth/d 0%
May Anomaly Digs  May 3 - 9 7 Days JL46/JL47 Anomaly digs Reduced Flows on JL46 Myton and JL47 Myton Segments
JL 46 Myton: 66,200 Dth/d
JL 47 Myton: 77,700 Dth/d
TBD TBD TBD
May Compressor Maintenance May 12 - 13 2 Days Kanda Compressor Station Station ESD Testing All Compression Offline
Kanda/Col CIG DEL MAP 171 shut in
Kanda/Col CIG REC MAP 871 shut in
Kanda/Col CIG DEL MAP 171: 178,000 Dth/d Kanda/Col CIG REC MAP 871:138,000 Dth/d
Kanda/Col CIG DEL MAP 171: 0 Dth/d 
Kanda/Col CIG REC MAP 871:0 Dth/d
ALL 100%
May Compressor Maintenance May 18 - 22 5 Days Leroy Compressor Station Station ESD Testing
No Injection or Withdraw at Leroy
Aquifer Storage Injection: 61,200 Dth/d
Aquifer Storage Withdraw: 134,900 Dth/d
Aquifer Storage Injection 31,200 Dth/d
 Aquifer Storage Withdraw: 74,900 Dth/d
0 Dth/d 0%
June Compressor Maintenance June 15 - 19  5 Days Thistle Creek Compressor Station  Station ESD Testing All Compression Offline
Lowered capacity on ML 104 Goshen Segment
ML 104 Goshen Segment: 384,500 Dth/d
ML 104 Goshen: 302,000 Dth/d
TBD TBD
July Compressor Maintenance July 7 - 8  2 Days Coleman Compressor Station Station ESD Testing All Compression Offline Kanda/Coleman Segment: 410,000 Dth/d TBD TBD TBD
October Reservoir Testing October 4 - 17 13 Days Clay Basin Annual Injection Test No physical withdraw allowed starting GD Oct 4 through GD Oct 6. 
GD Oct 6, constant 250 MMcf/day INJ rate. 
GD oct 7, constant 275 MMcf/day INJ rate. 
GD October 8 through GD October 15, reservoir shut-in Resume normal operations GD October 16.
Varies, See latest EBB TBD ALL 100%

Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.