Maintenance Construction Schedule - MountainWest Pipeline

2026 Schedule

Period Category Preliminary Dates Duration Location Project Possible Customer Impact Current Capacity (Dth/d) Restricted Capacity (Dth/d) Anticipated Firm Cut Quantity Anticipated Total Nomination Cut %
August Anomaly Digs Aug 17 - 30 15 Days ML 1, ML13, and ML15 from Nightingale to Eakin Anomaly Digs Taps switching lines. No impacts anticipated. No flow reduction or pressure restrictions. N/A N/A 0 Dth/d 0%
August

Pig

August 4 & 6

2 Days
ML 1 Nightingale to Eakin

Smart Tool
The Nightingale ML22 Segment capacity will be reduced from 206,650 Dth/d to 55,000 Dth/d.
The Nightingale ML22 Segment capacity is 206,650 Dth/d
The Nightingale ML22 Segment capacity will be reduced from 206,650 Dth/d to 55,000 Dth/d.
54 % 65,000 Dth/d
August



System Integrity

August 18-19

2 Days
Skull Creek Dew Point Plant MS

Meter Replacement
Shut-in MAP 967: 48,850 Dth/d MAP 167: 44,000 Dth/d
0 flow for MAPS 967 & 167 ALL 100%
August



Anomaly Digs

August 31-Sept 8

9 Days
ML 1 Eakin to Coleville

Anomaly Digs
None N/A N/A 0 Dth/d 0%
August Compressor Maintenance August 25-28  4 Days Blind Canyon Compressor Station Station ESD Testing All Compression Offline Varies, See latest EBB TBD TBD TBD
September Anomaly Digs Sept 8-18 11 Days ML22 and ML23 Skull Creek Compressor Anomaly Digs Capacity reduction on ML22 Nightengale segment, reduced pressures. Varies, See latest EBB TBD TBD TBD
October Reservoir Testing October 4 - 17 13 Days Clay Basin Annual Injection Test No physical withdraw allowed starting GD Oct 4 through GD Oct 6. 
GD Oct 6, constant 250 MMcf/day INJ rate. 
GD oct 7, constant 275 MMcf/day INJ rate. 
GD October 8 through GD October 15, reservoir shut-in Resume normal operations GD October 16.
Varies, See latest EBB TBD ALL 100%

Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.