Period | Category | Preliminary Dates | Duration | Location | Project | Possible Customer Impact | Current Capacity (Dth/d) | Restricted Capacity (Dth/d) | Anticipated Firm Cut Quantity | Anticipated Total Nomination Cut % |
---|---|---|---|---|---|---|---|---|---|---|
September - October | System Integrity | September 15 - 27 | 13 days | ML 23 | Line Lowering | ML23 Segment from 30,250 Dth/d down to 0 Dth/d,
ML26 Segment from 7,750 Dth/d down to 0 Dth/d, Nominations at West Side Canal MAP 9, Slater Dome MAP 344, Blue Gravel MAP 6, Bulldog MAP 423, Chandler MAP 3, and North Craig MAP 1 will only be allowed to deliver to Greeley Gas MAP 804. |
ML23 Segment 30,250 Dth/d ML26 Segment 7,750 Dth/d | ML23 Segment 0 Dth/d ML26 Segment 0 Dth/d Nominations at West Side Canal MAP 9, Slater Dome MAP 344, Blue Gravel MAP 6, Bulldog MAP 423, Chandler MAP 3, and North Craig MAP 1 will only be allowed to deliver to Greeley Gas MAP 804. |
TBD | TBD |
October | Reservoir Test | October 4 - 15 | 12 Days | Clay Basin | Annual Injection Test | No physical withdraws allowed from GD October 4 through GD October 6. - Tuesday, 10/07: reservoir conditioning at 225,000 Dth/d for 24 hrs; - Wednesday, 10/08: injection test at 250,000 Dth/d for 24 hrs; - Thursday 10/09 to Thursday, 10/16: field shut in. |
Varies, see latest EBB posting | October 7: 225,000 Dth/d October 8: 250,000 Dth/d October 9 - 15: 0 Dth/d |
ALL | 100% |
Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.