Period | Category | Preliminary Dates | Duration | Location | Project | Possible Customer Impact | Current Capacity (Dth/d) | Restricted Capacity (Dth/d) | Anticipated Firm Cut Quantity | Anticipated Total Nomination Cut % |
---|---|---|---|---|---|---|---|---|---|---|
October | Reservoir Test | October 4 - 16 | 12 Days | Clay Basin | Annual Injection Test | • October 4 through October 6: Reservoir conditioning begins. No withdrawals allowed. • October 7: The reservoir will be conditioned at a constant injection rate of 225,000 Dth for 24 hours. • October 8: Reservoir test at a constant injection rate of 250,000 Dth for 24 hours. • October 9 through October 15: Field shut in. Only in-place transfer nominations will be processed. • October 16: Field returns to normal at 8:00 AM. |
Varies, see latest EBB posting | October 7: 225,000 Dth/d October 8: 250,000 Dth/d October 9 - 15: 0 Dth/d |
ALL | 100% |
Note: This schedule is subject to change. It is recommended the Shippers monitor MountainWest Pipeline's critical notices about schedule revisions.