MAINT/CONSTRAINT | 07/25/2025 03:42 PM | 08/21/2025 09:00 AM | 36911 | WHITNEY CANYON BATTERY CHARGER REPLACEMENT | 1 | 5 |
MountainWest Overthrust Pipeline, LLC (MWOP) has updated the maintenance posting for work at Whitney Canyon. Please review all entries for upcoming work here: MountainWest Overthrust Pipeline, (MWOP): Construction and Maintenance Schedule (mwpipe.com) (www.mwpipe.com/MaintConstructionSchedule/MWOP)
The scheduled battery charger replacement at Whitney Canyon on August 21, 2025, will require a capacity reduction at:
• MAP 10002 from 264,083 Dth/d to 0 Dth/d
• MAP 10006 from 262,000 Dth/d to 0 Dth/d
• MAP 10015 from 220,000 Dth/d to 0 Dth/d
• MAP 10032 from 344,000 Dth/d to 0 Dth/d
• MAP 10832 from 344,000 Dth/d to 0 Dth/d
This reduction will begin Timely Cycle GD 8/21/2025 through cycle ID3 GD 8/21/2025. Nominations will return to normal Timely Cycle GD 8/22/2025.
This will be a 100% cut from firm nominations.
If you have any questions, please contact your MWP Marketing or Contract Services Representative, or Scheduling, via the Customer Service Hotline at 801-584-6034.