MountainWest Pipeline LLC (MWP) would like to update its customers with the following:
The programming issue with the inspection tool has been resolved. The smart pigging work on ML 1 (Nightingale to Eakin) that was delayed, has been rescheduled to take place starting Timely Cycle August 25, 2026, and lasting through the ID3 Cycle. To facilitate a successful pig run at the correct speeds, The Nightingale ML22 Segment capacity will be reduced from 206,650 Dth/d to 55,000 Dth/d.
If you have any questions, please contact your MWP Marketing or Contract Services Representative or the Customer Service Hotline on 801-584-6034.