| Notice Type Desc | Post Date/Time | Notice Eff Date/Time | Notice ID | Subject | Rsp Date/Time | Notice Stat | Prior Notice | Reqrd Rsp |
|---|---|---|---|---|---|---|---|---|
| FORCE MAJ/CONSTRAINT | 06/09/2026 08:30 AM | 06/09/2026 09:00 AM | 38651 | FORCE MAJEURE -UPDATE CLAY BASIN INJECTION CAPACITY | 2 | 38631 | 5 |
MountainWest Pipeline, LLC (MWP) reports that the mechanical issue at the Clay Basin Storage Facility has been resolved, and affected operations have been restored to normal conditions.
Based off current system and operating pressures, effective gas day June 9th, 2026, cycle ID1, Clay Basin injections will be increased to 175,000 Dth/d plus 25,000 Dth/d Park and Loan for a total injection capacity of 200,000 Dth/d.
If you have any questions, please contact your MWP Marketing or Contract Services Representative, or Scheduling on the Customer Service Hotline at 801-584-6034.